Summary Manpower in —: — / — people against plan; OPS teams ORR checklist at — vs plan —; — PRs late.
Items picked automatically from the data: late, overdue, expiring or below threshold.
Plan dates from the milestones table. Dates still to be confirmed show as TBC.
Headcount by month. Dashed line is plan; the vertical marker is the report date.
Weighted % complete by month. Dashed line is plan, solid line is actual.
Filled / required positions at the report date.
Vacant positions: —.
Courses completed vs required by the HSE training matrix.
Modules by status: completed, in review, in development.
Module development and theory / OJT assessment progress for each team.
| Platform | Team | Modules | Completed | % developed | % theory assessed | % OJT |
|---|
Every defined module with its document number, status and author.
| Team | No. | Module | Status |
|---|
Courses by month. Past months are dimmed.
Which HSE courses each position needs (PQ-MS-HSE-GDL-001-U01). Choose a position to list its courses.
Bar is actual %, black tick is plan %. The figure on the right is the gap in percentage points.
Total and completed activities; weights roll up into the overall %.
| Team | Weight | Activities | Completed | Final plan |
|---|
Cumulative plan % for each team by month, with the actual % below: green when on or ahead of plan, red when behind.
Sorted from lowest %. Elements below 50% are shown in red.
| Code | Element | Items | Progress |
|---|
Sorted by % complete, lowest first, so open procedures sit at the top.
| No. | Document | Due | Completed |
|---|
Sorted by % complete, lowest first, so open procedures sit at the top.
| No. | Document | Due | Completed |
|---|
— PRs. Each block is one PR, coloured by schedule status.
— packages in preparation, by status, priority and expected SCR timing.
Status of operations software systems.
Contracting route and next step.
Permits, reference number, issuing authority or responsible party, issue and expiry dates, and status.
| Permit | Issued | Expires | Status |
|---|
—
Planned start – finish. Green: completed (has an actual finish date); red: inside its planned window on the report date; amber: starts within the next 30 days.
Summarised from the CPP start-up block diagram.
Every figure compared with the copy saved at the end of an earlier day, item by item. Figures are cumulative, so a change is what moved since then.